WA Security of Payment Deadline Calculator

Calculate Western Australian Security of Payment Act 2021 deadlines: payment schedule, due date, notice and adjudication application dates.

This tool provides general estimates only and does not constitute legal advice. For advice specific to your situation, contact Vitt Legal for a consultation — expert, transparent legal advice.

The last day you did the work (or supplied the goods or services) covered by this claim. Used to check the time limit for serving a claim.

Payment Schedule Received?

How the calculator works

  1. You choose the state or territory where the work was done and who you are claiming from. Security of Payment laws are state-based, so the deadlines differ.
  2. From the date you served your payment claim, it counts forward the business days allowed for the payment schedule and the due date for payment, skipping weekends and any Christmas–New Year days the Act excludes.
  3. Depending on how the other side responded, it works out the last day to give a notice of intention (where one is required) and to apply for adjudication.
  4. Where a rule could not be confirmed from an official source, the calculator does not guess: it tells you to confirm that step with a lawyer.

Rules last checked .

Western Australia Security of Payment rules

Western Australia (WA)

Building and Construction Industry (Security of Payment) Act 2021 (WA)

Which contracts
Applies to contracts entered into on or after 1 August 2022. Earlier contracts fall under the Construction Contracts Act 2004 (WA).Source: WA Government — Subcontractor payment disputes (Security of Payment Act)
Counting business days
Business days exclude weekends, public holidays and 22 December to 10 January.Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Time limit to serve a payment claim
Progress claims: before the later of the contract date or 6 months after the work was last carried out (s 23(4)).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Payment schedule
15 business days after the claim is made, or earlier if the contract requires (s 25).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Due date — claiming from the principal
Principal to head contractor: 20 business days after the claim, or earlier if the contract says so (s 20).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Due date — claiming from a head contractor
To a subcontractor: 25 business days after the claim, or earlier if the contract says so (s 20).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Homeowner (owner-occupier) contracts
Home building work: the contract date; if the contract is silent, 10 business days after the claim (s 20(3)).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Adjudication — schedule for less than claimed
Within 20 business days after you first become entitled to apply (when you receive a schedule for less than claimed).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Adjudication — scheduled amount not paid
Within 20 business days after the due date passes without full payment.Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
Adjudication — no schedule and not paid
Give written notice within 20 business days after the due date; the respondent then has 5 business days to provide a schedule. Apply within 20 business days after you become entitled to (s 28).Source: Building and Construction Industry (Security of Payment) Act 2021 (WA)
  • A copy of the adjudication application must be given to the respondent within 1 business day after it is made.

Security of Payment deadlines by state

Maximum periods under each Act. A contract can shorten the payment schedule and due date periods. Adjudication periods run from the event shown.

StatePayment scheduleAdjudication: schedule for lessAdjudication: no scheduleClaim time limit
VIC10 business days10 business days after receiptNotice within 10 days of due date, 5-day second chance, then 5 business days6 months after practical completion (or contract, if later)
NSW10 business days10 business days after receiptNotice within 20 days of due date, 5-day second chance, then 10 business days12 months after work last done (or contract, if later)
QLD15 business days30 business days after receipt30 business days6 months after work last done (or contract, if later)
WA15 business days20 business days after receiptNotice within 20 days of due date, 5-day second chance, then 20 business days6 months after work last done (or contract, if later)
SAConfirm with a lawyerConfirm with a lawyer after receiptConfirm with a lawyerConfirm with a lawyer
TAS10 business days10 business days after receiptNotice within 20 days of due date, 5-day second chance, then 10 business days12 months after work last done (or contract, if later)
ACT10 business days10 business days after receiptNotice within 20 days of due date, 5-day second chance, then 10 business days12 months after work last done (or contract, if later)
NT10 working days65 working days after receipt65 working daysSet by the contract

What this calculator does not cover

  • Public holidays. They are not skipped, so a real deadline can be a day or more later than shown.
  • Earlier deadlines set by your contract, beyond the due date you enter.
  • Final payment claims, performance security and retention claims, and adjudication responses.
  • Contracts signed before the current rules started (see “Which contracts” for each state).
  • Whether your payment claim or schedule is valid, or whether the Act covers your contract at all.
  • South Australian dates, which could not be confirmed against the current Act.

Get help with a payment dispute

Need a Precise Quote?

Every matter is unique. Get expert, transparent legal advice and receive a tailored fee estimate for your specific circumstances.

CallBook a Consultation