Brisbane, QLD
In short
In Queensland, most building disputes start with the Queensland Building and Construction Commission (QBCC), not a court. Homeowners in Brisbane generally notify the builder in writing, lodge a QBCC complaint, and only then apply to QCAT. Contractors chasing payment use the Building Industry Fairness (Security of Payment) Act 2017, which has strict business-day deadlines. Planning appeals go to the Planning and Environment Court in George Street. First step: gather your contract, photos and dates, and check your time limits.
How building and construction disputes work in Queensland
Whether it is a renovation in New Farm, a new build in Newstead or an unpaid invoice on a Fortitude Valley fit-out, Queensland runs most building disputes through one regulator: the Queensland Building and Construction Commission (QBCC). The QBCC licenses builders and trades, handles complaints about defective work, runs the Queensland Home Warranty Scheme (the state's statutory home building insurance) and houses the registry for payment adjudications.
The main law is the Queensland Building and Construction Commission Act 1991 (Qld). Schedule 1B of that Act sets the rules for domestic building contracts. Work priced over $3,300 needs a written contract. For contracts of $20,000 or more, the builder must give you the QBCC consumer building guide before you sign. Deposits are capped, generally at 10% for contracts under $20,000 and 5% for contracts of $20,000 or more, with a higher cap where more than half the work is done off-site. You usually have a 5 business day cooling-off period after receiving the signed contract.
The Act also writes promises into every regulated contract, called statutory warranties. These are guarantees the law adds whether or not the contract mentions them, such as that work will be done with reasonable care and skill. Court or tribunal proceedings for a breach must generally be started within 6 years of completion for a structural defect, or 1 year for other defects, with a short extension if the problem appears in the last 6 months.
One rule catches many people out. You generally cannot take a building dispute to the Queensland Civil and Administrative Tribunal (QCAT) until you have been through the QBCC's dispute resolution process. QCAT expects a QBCC letter confirming the outcome when you file.
What can I do about defective or unfinished building work in Brisbane?
Start with your contract and put everything in writing. The QBCC expects you to give your contractor written notice of each defective or incomplete item and a reasonable time to fix it. Its guidance gives 14 days as an example. Keep photos, emails and reports.
If that does not work, you can lodge a defective work complaint with the QBCC. Timing matters. For non-structural defects, the QBCC says a complaint must be lodged as soon as possible and no later than 12 months from completion of the work. For structural defects, it must be lodged within 12 months of noticing the defect. The QBCC may inspect the work and can issue a direction to rectify, which is a legally binding order requiring the contractor to fix the work. The QBCC can only give that direction within 6 years and 6 months of the work being completed, unless QCAT extends the time.
Shorter deadlines apply if you may need to claim on the Queensland Home Warranty Scheme, for example because the builder cannot or will not come back to fix or finish the work. Structural defect claims must be made within 3 months of first noticing the defect. Non-structural defects must be noticed within 6 months of substantial completion and claimed within 7 months of substantial completion. If a builder does not finish, a non-completion claim must be lodged within 3 months after the contract ends. Missing these dates can cost you that safety net.
I have not been paid for construction work in Queensland. What are my options?
Builders, subcontractors and suppliers are protected by the Building Industry Fairness (Security of Payment) Act 2017 (Qld), often called the BIF Act. It gives you a fast, statutory right to progress payments, with tight timeframes on both sides.
A payment claim (a written demand for a progress payment, usually your invoice) must generally be given within 6 months after the work was last carried out, or any longer period your contract allows. The party receiving it must respond with a payment schedule, a written reply stating how much they will pay and why any amount is withheld, within 15 business days or any shorter period in the contract. If they do not respond and do not pay in full, they become liable for the whole claimed amount on the due date and cannot lodge a response in any later adjudication.
Adjudication is a quick decision on the papers by an independent registered adjudicator. You apply to the Adjudication Registrar at the QBCC. The deadline is 30 business days after you receive a payment schedule you disagree with, 20 business days after the due date if the scheduled amount was not paid, or 30 business days if no schedule was given and you were not paid, counted from the later of the due date and the last day a schedule could have been given. The Act counts business days in its own way: weekends, public holidays and the period from 22 December to 10 January are left out.
Adjudicators must generally decide within 10 business days of the response date for standard claims, or 15 business days for complex claims over $750,000.
The BIF Act payment claim process does not apply to domestic building work where a resident owner, meaning a person who lives or intends to live in the home, is a party to the contract. Those disputes follow the QBCC and QCAT path instead.
Challenging a council planning or development decision in Brisbane
Planning disputes follow a separate track under the Planning Act 2016 (Qld). If your local council refuses your development application, approves it with conditions you cannot live with, or issues you an enforcement notice about building work or land use, the usual forum is the Planning and Environment Court of Queensland. Neighbours who made a proper submission on certain applications may also have appeal rights.
The appeal period is short. For most decisions it is 20 business days after the decision notice or enforcement notice is given. A few appeal types have shorter periods. Some building-related matters can instead go to a development tribunal established under the Planning Act 2016. A tribunal decision can only be appealed to the court for an error of law or jurisdictional error, meaning the tribunal acted outside its powers.
The Planning and Environment Court says most cases resolve before a final hearing, and it offers a free alternative dispute resolution service run by its ADR Registrar. Costs are not automatically awarded against the losing party, although the court can make costs orders in some situations, such as where a party acts frivolously or ignores directions.
Where are construction and planning disputes heard near Fortitude Valley?
The QBCC's Brisbane customer service centre is at 488 Lutwyche Road, Lutwyche, a few kilometres north of the Valley. Complaints and adjudication applications can be lodged online through the QBCC Portal. Adjudication applications must reach the Registrar before 5.00pm on a business day to count as lodged that day.
QCAT's registry and hearing rooms are at Level 8, 259 Queen Street in the Brisbane CBD. QCAT has no monetary limit for domestic building disputes. For commercial building disputes, it can decide claims of up to $50,000, or more only if all parties consent in writing. Parties are generally expected to represent themselves at QCAT unless the tribunal gives permission for a lawyer, although you do not need permission to get legal help preparing your application, evidence and submissions.
The Planning and Environment Court's Brisbane registry is in the QEII Courts of Law Complex, 415 George Street, Brisbane. Appeals must be filed in person or by post, because the court does not accept electronic lodgement. Commercial claims outside QCAT's limit go to the Magistrates, District or Supreme Court, depending on the amount.
How Queensland differs from other states
Every state has its own building laws. Queensland concentrates licensing, defect complaints, statutory home warranty insurance and the adjudication registry in a single body, the QBCC, and makes QBCC dispute resolution a gateway to the tribunal. In New South Wales, by comparison, home building is governed by the Home Building Act 1989 (NSW), and security of payment by a separate 1999 Act with its own timeframes. If your project, contract or builder is connected to another state, do not assume Queensland deadlines apply.
Key Queensland legislation
- Queensland Building and Construction Commission Act 1991 (Qld) (opens in a new tab)
Sets up the QBCC, builder licensing, directions to rectify, the Queensland Home Warranty Scheme and, in Schedule 1B, the rules and statutory warranties for domestic building contracts.
- Building Industry Fairness (Security of Payment) Act 2017 (Qld) (opens in a new tab)
Gives contractors, subcontractors and suppliers the right to progress payments, with fixed timeframes for payment claims, payment schedules and adjudication.
- Planning Act 2016 (Qld) (opens in a new tab)
Governs development applications, enforcement notices and appeal rights, including the 20 business day appeal period for most decisions.
- Planning and Environment Court Act 2016 (Qld) (opens in a new tab)
Sets the powers and procedures of the Planning and Environment Court, including its approach to costs.
- Queensland Civil and Administrative Tribunal Act 2009 (Qld) (opens in a new tab)
Establishes QCAT and the procedures it uses when deciding building disputes and reviewing QBCC decisions.
Courts and tribunals in Queensland
- Queensland Building and Construction Commission (QBCC) (opens in a new tab)
The state building regulator. Handles defective work complaints, issues directions to rectify, administers the Queensland Home Warranty Scheme and hosts the Adjudication Registry for BIF Act payment disputes. Brisbane customer service centre: 488 Lutwyche Road, Lutwyche Qld 4030.
- Queensland Civil and Administrative Tribunal (QCAT) (opens in a new tab)
Decides domestic building disputes with no monetary limit and commercial building disputes up to $50,000 (more with written consent of the parties), and reviews certain QBCC decisions. QBCC dispute resolution must be attempted first. Registry: Level 8, 259 Queen Street, Brisbane.
- Planning and Environment Court of Queensland (opens in a new tab)
Hears appeals about development application decisions, infrastructure charges and enforcement notices, appeals from development tribunal decisions on errors of law or jurisdictional error, and applications for enforcement orders and declarations. Brisbane registry: QEII Courts of Law Complex, 415 George Street, Brisbane Qld 4000.
- Magistrates, District and Supreme Courts of Queensland (Brisbane) (opens in a new tab)
Hear construction contract and debt claims that fall outside QCAT, including larger commercial disputes and enforcement of adjudicated amounts. QBCC guidance: Magistrates Court for debts up to $150,000, District Court above $150,000 up to $750,000, Supreme Court above $750,000. An adjudication certificate can be filed as a judgment debt in a court of competent jurisdiction.
How the process works
Check the contract and the dates
Gather the signed contract, variations, invoices, photos and correspondence. Work out the completion date, when you first noticed the problem or when payment fell due, because Queensland time limits run from these dates.
Give written notice to the other side
Homeowners give the contractor written notice of each defect or incomplete item and a reasonable time to fix it. Contractors seeking payment serve a valid payment claim under the BIF Act, and respondents reply with a payment schedule within the required time.
Use the QBCC process
If notice does not resolve things, lodge a defective work or contract dispute complaint with the QBCC, or apply to the QBCC Adjudication Registrar for adjudication of an unpaid payment claim. The QBCC may inspect the work and can issue a direction to rectify.
Consider a home warranty claim
Where the builder cannot or will not fix or finish residential work, a claim under the Queensland Home Warranty Scheme may be available. The claim deadlines are shorter than the general complaint deadlines.
Apply to QCAT or a court
If the dispute continues, apply to QCAT with the QBCC outcome letter, or start court proceedings for larger commercial claims. For planning matters, file a notice of appeal in the Planning and Environment Court within the appeal period.
Negotiate, mediate or proceed to a hearing
Many matters settle through negotiation, tribunal-directed dispute resolution or the Planning and Environment Court's ADR process. If not, the tribunal or court decides the matter on the evidence.
Time limits in Queensland
| Step or claim | Time limit | Source |
|---|---|---|
| QBCC complaint about non-structural defective work | As soon as possible and no later than 12 months from completion of the work | https://www.qbcc.qld.gov.au/complaints-disputes/building-work-issue/defective-work-dispute/help-defective-work |
| QBCC complaint about structural defective work | Within 12 months of noticing the defect; the QBCC can only issue a direction to rectify within 6 years and 6 months of the work being completed | https://www.qbcc.qld.gov.au/complaints-disputes/building-work-issue/defective-work-dispute/help-defective-work |
| Queensland Home Warranty Scheme claim for a structural defect | Within 3 months of first becoming aware of the defect, and the defect must become apparent within 6 years 6 months of cover starting | https://www.qbcc.qld.gov.au/home-owner-hub/queensland-home-warranty-scheme/time-limits-cover-claims |
| Payment schedule in response to a BIF Act payment claim | 15 business days after the payment claim is given, or any shorter period in the contract (section 76); not required if the full claimed amount is paid by the due date. BIF Act business days exclude 22 December to 10 January | https://www.legislation.qld.gov.au/view/whole/html/inforce/current/act-2017-043 |
| Adjudication application under the BIF Act | 30 business days after receiving a payment schedule for less than the amount claimed; 20 business days after the due date if the scheduled amount is unpaid; 30 business days where no schedule was given and the claim is unpaid (section 79) | https://www.qbcc.qld.gov.au/complaints-disputes/payment-contract/commercial-payment-dispute/adjudication/apply-adjudication |
| Appeal to the Planning and Environment Court | For most decisions, 20 business days after the decision notice or enforcement notice is given (Planning Act 2016, section 229) | https://www.legislation.qld.gov.au/view/whole/html/inforce/current/act-2016-025 |
Costs
Cost in a Queensland building matter depends mainly on the forum and the evidence needed: a QBCC complaint is a different exercise from a QCAT hearing with independent building reports, a BIF Act adjudication (where the QBCC charges an application fee scaled to the claim and adjudicator fees apply), or a Planning and Environment Court appeal with filing fees and town planning consultants. The amount in dispute, the number of defects and how early the parties negotiate also matter. Vitt Legal provides a written costs disclosure before any work starts.
Construction, Building & Planning Disputes services we handle
These are our general service guides. They explain each service in detail but are not written for Queensland specifically, so read them together with the information on this page.
- General guideBuilding Defects, Variations & Payment DisputesMelbourne advice on building defects, delay, variations, payment disputes, DBDRV and security of payment strategy.
- General guideDomestic Building Insurance & Warranty ClaimsMelbourne advice on domestic building insurance, statutory warranty claims and related residential construction disputes.
- General guidePlanning Permit Reviews & AppealsMelbourne planning permit advice and VCAT representation for permit refusals, conditions and objection disputes.
- General guideCouncil, Planning & Building EnforcementMelbourne legal advice on council notices, planning enforcement, building orders and related VCAT review matters.
Helpful tools
These tools give general estimates only. Some were built around the law of one state, so check the result with a lawyer.
What our Brisbane clients say
“After my workplace accident, I wasn't sure I had a case. Vitt Legal assessed my situation honestly and secured compensation that covered all my medical expenses and lost income.”
Nathan C. · Brisbane
“When our company faced financial difficulty, Vitt Legal provided clear, practical advice on our restructuring options. Their guidance helped us avoid liquidation and get back on track.”
Karen F. · Brisbane
“I needed advice on a non-compete clause before accepting a new role. The consultation was efficient, the advice was practical, and I felt confident making my decision. Great service.”
Daniel O. · Brisbane
Construction, Building & Planning Disputes in Brisbane: frequently asked questions
Do I have to go to the QBCC before QCAT for a building dispute in Queensland?
Generally, yes. Under the Queensland Building and Construction Commission Act 1991, a person cannot apply to QCAT about a building dispute unless they have first complied with the QBCC's dispute resolution process. QCAT asks for a letter from the QBCC confirming the outcome, or confirming that no process was required, when you file. Without it, QCAT may refuse to accept the application or may dismiss it.
How long do I have to complain about defective building work in Brisbane?
The QBCC says complaints about non-structural defects must be lodged as soon as possible and no later than 12 months from completion of the work. Complaints about structural defects must be lodged within 12 months of noticing the defect. The QBCC can only direct a contractor to rectify work within 6 years and 6 months of completion, unless QCAT extends that time. Home warranty claim deadlines are shorter, so check those as well.
What does the Queensland Home Warranty Scheme cover and when must I claim?
The scheme is Queensland's statutory insurance for most residential building work valued at more than $3,300, with the premium paid by the contractor. It can help with non-completion and with defects. Structural defect claims must be made within 3 months of first noticing the defect. Non-structural defects must be noticed within 6 months of substantial completion and claimed within 7 months. Non-completion claims must be lodged within 3 months after the contract ends.
I received a payment claim under the BIF Act in Queensland. What happens if I ignore it?
Ignoring it is risky. Unless you pay the full amount by the due date, you must give a payment schedule within 15 business days, or sooner if the contract says so. If you do not, you become liable for the full claimed amount on the due date, and you are not allowed to lodge an adjudication response if the claimant applies for adjudication. Failing to respond is also an offence and grounds for QBCC disciplinary action.
Can a homeowner in Brisbane be served with a BIF Act payment claim?
The progress payment provisions of the Building Industry Fairness (Security of Payment) Act 2017 do not apply to a contract for domestic building work where a resident owner is a party, to the extent it relates to the home the owner lives in or intends to live in. Payment disputes between a resident owner and their builder are instead handled through the contract, the QBCC's dispute process and QCAT. Investors and owner-builders may be treated differently.
How much can QCAT award in a Queensland building dispute?
For domestic building disputes, QCAT has no monetary limit. For commercial building disputes, QCAT can decide the matter if the amount in dispute is not more than $50,000. If the claim or counter-claim is more than $50,000, QCAT can only decide it if the parties consent in writing, and that consent must be filed with the application. Otherwise, larger commercial claims go to the courts.
How long do I have to appeal a Brisbane council development decision?
Under section 229 of the Planning Act 2016, the appeal period for most decisions, including enforcement notices, is 20 business days after the notice of the decision is given. An appeal against a deemed refusal, where the council has not decided in time, can be started at any time after the deemed refusal. Appeals are filed with the Planning and Environment Court, whose Brisbane registry is at 415 George Street.
Do I need a lawyer at QCAT or the Planning and Environment Court in Brisbane?
Not necessarily. QCAT generally expects parties to represent themselves, and you usually need the tribunal's permission to be legally represented at a hearing, although there are exceptions. Many people still get legal help preparing their application, evidence and submissions. In the Planning and Environment Court you may represent yourself or be represented by a lawyer or an agent, and the court encourages early dispute resolution through its free ADR service.
Construction, Building & Planning Disputes in other cities
Other legal services in Brisbane
- Family Law in Brisbane
- Criminal Law in Brisbane
- Employment & Workplace Disputes in Brisbane
- Commercial Disputes & Litigation in Brisbane
- Property Law & Conveyancing in Brisbane
- Migration Law in Brisbane
- Intellectual Property Law in Brisbane
- Defamation & Reputation Protection in Brisbane
- Commercial & Franchise Law in Brisbane
- Wills & Estates in Brisbane
- Insolvency & Restructuring in Brisbane
- Personal Injury in Brisbane
Expert Legal Help
Ready to Take the First Step?
Don't navigate legal challenges alone. Our experienced team is here to provide compassionate, expert guidance every step of the way.

